PS&TT2 Technical Stops and Shutdown Archives

Archives

PS/TT2 Planning YETS 2015-2016

release version EDMS 1510007

 

Access Constraints

General Access 6am to 21pm Open Close
PS ring and TT2 Line Wed 16/12/15@ 07.00 Fri 12/02/16 @ 12.00

 

Access Control  CCC<=>CSA Mon 04/01/16 @06.00 Fri 12/02/16 @06.00

 

 
     
Access from to Dur
TT2 lift (AS35) Not available Tue 18/12 @10.00 Tue 18/12 @12.00 2 h
YEA01.SWY=151 Not available Mo 11/01 @08.00 Fri 05/02 @17.00 20 d
TT2 lift (AS35) Not available Tue 15/01 @10.00 Tue 15/01 @12.00 2 h
PS Evacuation alarm Mo 18/01 @06.00 Mo 18/01 @08.00 2 h
TT2 Evacuation alarm Fri 22/01 @06.00 Fri 22/01 @08.00 2 h
TT2 lift (AS35) Not available Tue 02/02 @10.00 Tue 02/02 @12.00 2 h
YEA02.PSR=352 Not available Tue 08/02 @08.00 Tue 08/02 @18.00 8 h
PSR-SWY switch Siemens->Benning Fri 12/02 @12.00 Fri 12/02 @14.00 2 h
TT2 Fri 12/02 @08.00 Fri 12/02 @10.00 2 h
 
Blind Access Duration Activity Date Date
YEA02.PSR=352 2*1day CRPR-00040 Mon 04/01/16 Tue 05/01/16
YEA02.PSR=352 2*1day CRPR-00040 Mon 11/01/16 Tue 12/01/16
YEA02.PSR=352 2*1day CRPR-00040 Mon 18/01/16 Tue 19/01/16
YEPZ03.PSR=152 1*1day Cabling campaign Tue 19/01/16 Tue 19/01/16
YEA02.PSR=352 1*0.5day 4 MTV bldg 352 Thu 21/01/16 Thu 21/01/16
YEA02.PSR=352 1*0.5day CRPR-00040 Fri 22/01/16 Fri 22/01/16
YEA01.PSR=151 1*0.5day Cabling Mon 25/01/16 Mon 25/01/16
YEAxx.PSR=352/152 1*0.5day Waste Rem Wed 27/01/16 Wed 27/01/16
YEA02.PSR=352 1*0.5day QDE01-F61N Tue 02/02/16 Tue 02/02/16
YEA01.SWY=151 3*1hrs

3 Septa exchange

(13-01-03)

13/01/16 03/02/16
YEA02.PSR=352 1*0.5day Shielding Wed 03/02/16 Wed 02/02/16
YEA02.PSR=352 1*0.5day Shielding Thu 04/02/16 Thu 02/02/16
     
ATS-PM-MS-0001 EDMS 1470895
CERN's Complex EYETS 2016-2017 Planning
PS/TT2 Draft Planning EYETS 2016-2017 EDMS 1530458
 
Access 6am to 21pm Open Close
PS ring and TT2 Line Thur 15/12/16 @6.00 Thu 30/03/17 @18.00

Constraints

 

Access Constraints

Access 6am to 21pm Open Close
PS ring and TT2 Line Thur 15/12/16 Thur 22/12/16 @16.00
PS ring and TT2 Line Wed 04/01/17 Thu 30/03/17 @18.00

 

Access Control transfer CCC<=>CSA Thur 15/12/16 Wed 21/12/16 @16.00
Access Control transfer CCC<=>CSA Thur 05/01/17 Fri 31/03/17 @07.00

 

 
     
Access from to Dur
TT2 lift (AS35) Not available 16/12 16/12 2 h
PS Evacuation alarm 6am to 8am 20/01 20/01 2 h
TT2 Evacuation alarm 7am to 8am 19/01 19/01 2 h
PSR-SWY switch Siemens->Benning 15/03 15/03 0.5d
SWY-PSR doors from 16/01 - 24/01 16/01 24/01 2h
TT2 doors 30-31/01 30/01 31/01 2 h
TT2 lift (AS35) Not available 09/02 pm 4 h
Reception new Fire detection 14/03 pm 4h
 
Blind Access

Duration

Morning

Activity Date Date
YEA01.PSR=151 2*0.5day Storage Room has has to be emptied 15/12/2016 16/12/2016
YEA01.PSR=151 2*0.5day cabling 19/12/2016 20/12/2016
YEA01.PSR=151 3*0.5day Cabling campaign 05/01/2017 09/01/2017
YEA01.PSR=151 3*0.5day Crane tests + EO line removal 10/01/2017 12/01/2017
YEA01.PSR=151 2*0.5day New sectorisation  PS-Y-EC-0001 30/01/2016 31/01/2016
YEA01.PSR=151 2*0.5day EO line removal 03/02/2017 06/02/2017
YEA01.PSR=151 1*0.5day Septum 42 08/02/2017 08/02/2017
YEA01.PSR=151 1*0.5day MU41 10/02/2017 10/02/2017
YEA01.PSR=151 2*0.5day MU 13/02/2017 14/02/2017
YEA01.PSR=151 1*0.5day MU 16/02/2017 16/02/2017
YEA01.PSR=151 1*0.5day MU42 17/02/2017 17/02/2017
YEA01.PSR=151 1*0.5day MU41 27/02/2017 27/02/2017
YEA01.PSR=151 1*0.5day MU42 02/03/2017 02/03/2017
YEA01.PSR=151 1*0.5day MU 03/03/2017 03/03/2017
YEA01.PSR=151 1*0.5day MU42 06/03/2017 06/03/2017
YEA01.PSR=151 1*0.5day Septum 14/03/2017 14/03/2017
YEA02.PSR=352 1*0.5day Scan Access point 15/03/2017 15/03/2017
YEA01.PSR=151 7*0.5day Cabling

22/03/2017

28/03/2017
     